Massachusetts is initiating efforts toward its 2024 goal of procuring 5 GW of energy storage by 2030. A draft request for proposals (RFP) for 1.5 GW of 4- to 10-hour energy storage resources has been released. This initial RFP follows the state’s 2024 legislation mandating the procurement of 5 GW of storage capacity by 2030.
The exact release date for the Long-Term Contracts for Energy Storage Projects remains “TBD,” though a tentative schedule in the draft suggests a public release of the RFP on July 31, 2025.
The RFP includes scheduled periods for questions and feedback through the fall, with proposal submissions due by Sept. 10. Project selections will be announced approximately three months later, on Dec. 9, 2025.
The procurement will include National Grid, Eversource Energy, and Unitil, the three investor-owned utilities responsible for the majority of Massachusetts’ electrical infrastructure. These utilities will procure 45.1%, 53.89%, and 0.97%, respectively, of the total 1.5 GW capacity.
Projects must range in size from 40 MW to 1,000 MW. Bidders will pay a fee of $500 per MW, potentially generating $750,000 if the RFP is fully subscribed. The program is expected to attract significant interest, possibly leading to oversubscription. Upon executing long-term storage contracts, developers must provide a security deposit of $40,000 per MW, totaling up to $60 million.
With estimated costs around $200/kWh, total project value could range from $2.8 billion to $7 billion, depending on the chosen storage capacities.
A state-commissioned third-party analysis estimates annual revenue at just over $220/kW, primarily derived from the Clean Peak Standard (CPS) program. CPS incentivizes energy storage during “Seasonal Peak Periods,” identified by the state as times of peak demand and emissions. Massachusetts established the Clean Peak Program in 2018, following Vermont’s regional lead with its Tesla battery installations.
Revenue under CPS is paid via Clean Peak Energy Certificates (CPEC), each representing one megawatt-hour of certified clean electricity delivered during the Seasonal Peak Period.
Some of the project evaluation considerations include:
- Bid value under the CPEC program
- Evaluation of resilience and reliability value adders
- Proximity to major electrical loads
- Proximity to intermittent renewable energy sources
- Separation from other energy storage systems
- Safety measures and stakeholder engagement
- Credibility of proposed commercial operation dates, based on:
-
- Initiation and completion plans for permitting
- Resource and environmental assessments
- Detailed financing information and plans
- Installation and interconnection strategies
- Progress in acquiring necessary real property rights
- Material progress toward the acquisition of all real property rights
- Viable installation and electrical interconnection plans
Proposals must adhere to organizational standards outlined in the RFP package (below), which also contains contract templates guiding the procurement process.
The energy storage procurement aligns with Massachusetts’ 2024 legislation, An Act Promoting a Clean Energy Grid, Advancing Equity and Protecting Ratepayers, which directs the state to procure energy storage totaling 5 GW by July 31, 2030.
The procurement targets 3.5 GW of mid-duration storage (four to ten hours), totaling 14,000 to 35,000 MWh. An additional 750 MW will be long-duration storage (10 to 24 hours), and another 750 MW will require capacities exceeding twenty-four hours.
Overall, the initiative complements the 5 GW peak output with at least 39,500 MWh of storage capacity. Notably, New England’s peak load has significantly dropped, from nearly 25 GW five years ago to just below 4 GW, driven largely by growing solar installations.
The current law expands upon the 2018 goal of deploying 1,000 MWh of storage by Dec. 2025. As of Feb. 15, 2025, Massachusetts utilities reported “644 MWh of installed energy storage with an additional 12,932 MWh of storage in the pipeline.”
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.