Less than a year after it entered service, the Moss Landing Energy Storage Facility in California was forced offline on September 4 when an unspecified number of batteries overheated.
Local fire crews were called around 8 pm to a reported structure fire, but no fire was found. News reports said that first responders instead found battery racks that had been scorched and wires melted. Fire crews remained on the scene into Sunday.
In a statement, Vistra said that the storage facility experienced “an overheating issue with a limited number of battery modules.” The incident affected the facility’s Phase I 300 MW /1200 MWh system.
Vistra said that risk mitigation and safety systems “worked as designed” and detected that modules were operating at a temperature above operational standards. The company said that targeted sprinkler systems were activated and aimed at the affected modules. Vistra said that the overheating was “controlled and contained” without the need for outside assistance.
Vistra said it would keep the entire facility offline as it investigates the root cause of the incident in partnership with its engineering contractor, Fluence, and battery manufacturer, LG Energy Solution. Vistra was uncertain on the timing of the return of the facility, pending an investigation and any needed repairs.
A spokesperson for Vistra told pv magazine in an email that the company cautioned against insinuating that the batteries caused the incident. “We are very early in our investigation and have not determined a root cause,” the spokesperson said.
The Phase II 100 MW system, which is located in a separate building on site and entered service in August, was not affected by the event. It is currently available for operation.
Fire safety
The 300 MW Moss Landing facility that suffered the battery overheating event entered service in December. The adjacent second phase entered service in mid-August and included 4,500 TR1300 battery racks from LG Energy Solution.
When the second phase entered service, LG said that its lithium-ion-based batteries met fire safety standards, and that its racks had been tested to verify compliance with UL9540A (Standard for Safety Test Method for Evaluating Thermal Runaway Fire Propagation in Battery Energy Storage Systems), to ensure any fire event would not be propagated to adjacent battery racks.
The TR1300’s rack design also meets the American Society of Civil Engineers’ ASCE 7-16, assuring its stable operation even during external environmental changes such as seismic tremors. The standard is now part of the California Building Code.
LG has been working to improve its battery technology since an April 2019 accident involving one of the company’s utility-scale lithium-ion battery arrays at an Arizona Public Service location. A thermal runaway event there caused an accumulation of gases in the container that housed the batteries. Those gases ignited when first responders opened an access door to investigate reports of smoke coming from the container. Two firefighters were seriously injured.
Replacement
In late May, LG Energy Solution said it would replace, at its own cost, lithium-ion battery cells used for certain energy storage products that were manufactured between April 2017 and September 2018. The replacement program came after overheating incidents were reported.
The company said in a statement that it determined that there were issues in the early production processes for electrodes used in potentially affected batteries. Reports said the batteries were produced at the company’s Nanjing factory in China. The replacement program could cost around $350 million.
New batteries will incorporate manufacturing process improvements. The company said it also would implement remote modifications to reduce the potential for overheating while owners wait for their replacement units. LG Energy Solution also will update its battery diagnostic and control software. And it said that field inspections would be undertaken to monitor and minimize the potential for further incidents.
This article was updated on September 7 to clarify that Phase I of the facility entered service in December 2020 and was affected by the overheating incident.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
It’s foolish to use a flammable battery setup when such high current loads are involved.
Systems that are designed for high heat (Ambri, etc) AND don’t require complicated BMS or fire suppression is the obvious choice.
Seems more foolish to use a unproven technology on a 1.2GWh battery system; plenty of high current lithium battery systems deployed globally. If this is LG, there was an issue with the pouch design, perhaps this is that. I hear no HVAC was implemented on this site, not sure if the owner decided to install HVAC or not.
Pretty much 3.5 yrs of LG pouch cell production needs to be replaced. Maybe that is why LG split it off last yr from the main corporation.
The best engineering is always fine tuned by the real world, nothing unusual to see here!