AES Corporation has scrapped plans for the 320 MW / 1,280 MWh Seguro energy storage project in San Diego County, withdrawing its application after a three-year battle with North County residents.
The developer formally notified county officials of the exit, marking a decisive win for the “Stop Seguro” grassroots movement that had fought the lithium-ion facility since its inception.
(Read: “The community warning signs that can make or break a battery project”)
While the Stop Seguro group provided the friction, several technical and regulatory barriers ultimately made the project untenable for the developer. A critical blow came when the Palomar Health board of directors rejected a request for an easement through hospital grounds, cutting off the project’s only viable path to connect to the nearby SDG&E Escondido Substation. Without this connection, the facility’s business model effectively collapsed.
Local government and fire officials also closed off remaining paths for the project as the Escondido City Council enacted a moratorium on new battery storage systems within city limits. Simultaneously, the San Marcos Fire Protection District and the county fire chief adopted stricter safety codes requiring 100-foot setbacks from residential and educational lot lines. These new siting requirements would have forced AES to drastically shrink the footprint of the facility, further undermining its economic feasibility.
“While AES is no longer moving forward with the proposed Seguro project as we prioritize other projects, we remain committed to advancing projects that can provide the safe, reliable, and affordable power needed to strengthen the region’s electric grid and generate meaningful economic benefits locally,” said the company in a statement.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.






By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.