Utility scale solar inverters need improved commissioning and upkeep

Share

The North American Electric Reliability Corporation (NERC) has released a report, Multiple Solar PV Disturbances in CAISO, which discusses why more than 100 utility scale solar plants and a significant amount of distributed solar shed gigawatts of capacity during grid fault events in the spring and summer of 2021. This document complements the Odessa Disturbance, with NERC building upon the recommended policy changes.

The cascading nature of these events — due to the failure of a single piece of hardware — is reminiscent of the Northeast Blackout of 2003.

The reports do, optimistically, point toward the solvable nature of many of these issues via additional commissioning requirements, and possibly via high-level data monitoring. Some of the issues include onsite operations and maintenance teams that were not able to access passwords to equipment onsite, and were unable to change inverter settings.

However, it is clear that there is an issue, since there have been four events within the CAISO region within about two months time. Between these events, a cumulative 3.1 GW of capacity was dropped.

The four events were touched off by a phase-to-phase fault on a 500 kV line, two fires and their smoke that set off nearby 500 kV lines, and a tripped transformer that connected a 500 kV and 500/230 kV set of lines.

The solar facilities reacted in a variety of ways, and analysis found many individual faults within the plants that led to the gigawatts of shed generation. Most of the capacity that was shed did immediately return to generation, however, several large blocks of generation took longer to get back online.

One of the broader issues stemmed from a lack of data collectors in specific places, which meant that NERC was unable to obtain explicit data showing why these sites stayed down longer than intended. NERC hypothesized that this was the result of inverter settings, though unfortunately, those settings are not available.

To head off the issue of not knowing for sure where the issues are, NERC ‘strongly recommends all newly connecting bulk power system (bps)-connected inverter-based resources to be equipped with at least the following’ pieces of data collecting gear:

  • SCADA data throughout the plant (1-second resolution)
  • Sequence of events recording at all logging points within the plant and at inverters (1-ms resolution)
  • Plant-level continuous recording from a phasor measurement unit or plant-level controller (1–2 cycle reporting resolution)
  • Plant-level digital fault recorder (DFR) data from a digital relay or the plant-level controller (kHz resolution oscillography)
  • Inverter-level oscillography data to capture inverter terminal behavior, at least from some
  • Inverters within the plant (kHz resolution)

Additionally, simply having better access to records and passwords of facilities was high on the list of needed improvements. The report notes that as plants have changed hands, the operations and maintenance teams haven’t always been given proper records of hardware installed or replacement records. This is in addition to simply not having passwords.

The password issue was made more challenging by multiple inverter manufacturers that have gone out of business, suggesting that the in-house password workarounds that might exist within the IT teams could be lost to the fog of corporate evolution.

Most of the additional recommendations unique to the CAISO report versus the initial Odessa report can be summarized as NERC pushing CAISO to implement standards they had previously recommended, and for better monitoring of sites.

If anything, the people working on reliability appear to be zeroing in on a specific set of challenges.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Popular content

Solar companies unite in Helene disaster relief in North Carolina
07 October 2024 Greentech Renewables Raleigh, Footprint Project, Land of Sky Regional Council of Governments, and the NC Sustainable Energy Association are partnering...