U.S. could lose 60 GW of solar if Trump’s “start of construction” rules tighten

Share

The United States could lose 60 GW of planned solar installations through 2030 if the Department of Treasury enforces a strict interpretation of the “start of construction” qualifier for the clean energy Investment Tax Credit and Production Tax Credit, said Clean Energy Associates (CEA).

A July 8 executive order from President Trump instructed the Department of Treasury to tighten restrictions on solar tax credits.

Under the new Republican budget, solar projects that  reached “start of construction” within 12 months of enactment, or were “placed in service” by 2028, are eligible for the 45Y Production Tax Credit and the 48E Investment Tax Credit . Such projects would be eligible for the credits under a safe harbor provision.

CEA said strict start-of-construction language could derail about 60 GW projects hoping to take advantage of safe harboring credits until 2030.

Image: CEA

The executive order directs the Treasury to restrict safe harboring of projects, tightening interpretation of the “beginning of construction” language. The order requires that a “substantial portion” of a project must be built to secure credits. The order requires  the Treasury to enforce this within 45 days of the enactment of the congressional budget bill.

Keith Maritn, partner, Norton Rose Fulbright, said to qualify for safe harbor designation, projects likely will need to “incur” at least 5% of the project’s cost.

“Costs are usually incurred only as the developer takes delivery of equipment or services, with one exception. A payment for specific equipment or services by the deadline counts if delivery is reasonably expected within 3 1/2 months. There are nuances about counting payments for services,” said Martin.

The other path to qualification, he said, is to start “physical work of a significant nature” at the project site on the portions of the project eligible for the 48E credit.

“For years, developers and investors have relied on these rules to qualify projects under the ITC/PTC framework, even when [commercial operation date] occurs years later,” said Peter DeFazio, managing partner, Greenprint Capital. “If interpreted narrowly, projects that haven’t meaningfully advanced beyond paper progress—even with a 5% basis spend—could lose eligibility.”

DeFazio said if the application of this stricter interpretation is retroactive, the fallout would ripple across billions in project pipeline capital.

“Now is the time to review safe harbor assumptions, revisit NTP timelines, and assess whether your portfolio could be exposed,” said DeFazio.

The early loss of tax credits are expected to deal long-term damage to the industry. Wood Mackenzie forecast 10-year installations could decrease 17%, reaching volumes as low as 375 GW for the decade.

“Permitted projects are well-positioned, but unpermitted developments face growing uncertainty as permitting bottlenecks threaten to push completion dates outside eligibility windows,” said a press statement from Wood Mackenzie.

CEA said Trump could take other anti-solar actions, such as pushing for punitive tariffs on equipment, like the far-reaching polysilicon Section 232 tariffs, have the Treasury revise qualification methods, or set additional requirements for project developers.

Tariff enforcement also remains an ongoing threat to solar project development. CEA said PV module, bill of materials, and power plant components could face up to five different tariffs. A summary table is shown below.

Image: CEA

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Popular content

Polysilicon solar manufacturing facility to be built on abandoned nuclear project site in Tennessee
11 August 2025 Highland Materials' manufacturing facility will have an initial annual capacity of 16,000 metric tons of solar-grade polysilicon.