Despite all of the factors that made 2020 the year it was, Duke Energy reports that it was a record-breaking year for the company in North Carolina, with roughly 5,500 residential and commercial customers in the state installing solar systems last year.
The company attributes a significant portion of this installation figure to its five-year, $62 million rooftop solar rebate program.
Residential customers who are approved for rebates will get a $0.60/W credit for their installed solar system, up to 10 kW or $6,000, while businesses are eligible for a $0.50/W credit and nonprofits are eligible for $0.75/W. These nonresidential projects cap out at 100 kW of installed capacity, meaning a maximum credit of $50,000 for businesses and $75,000 for nonprofits.
In the company’s own solar pursuits, Duke connected nearly 350 MW of solar capacity in North Carolina last year, headlined by the 69 MW Maiden Creek solar facility in Catawba County and the 25 MW Gaston County solar facility in Bessemer City.
While not as substantial in the capacity department, Duke also came to an agreement with the U.S. Army’s Fort Bragg to install a 1.1 MW floating solar system on Camp Mackall’s Big Muddy Lake, as part of a $36 million energy services effort.
These capacity additions helped Duke to reach the milestone of having more than 3.7 GW of solar capacity connected to its energy grid in North Carolina. The company also reached its goal of owning and contracting for 8 GW of wind, solar, and biomass generation around the nation, a goal which has since been doubled to 16 GW by 2025.
2020 was also a milestone year for Duke’s Green Source Advantage (GSA) program, which allows large-scale customers to offset power purchases by securing renewable energy from projects connected to the Duke Energy grid. In 2020, the utility came to terms with the City of Charlotte, Bank of America, and Duke University on GSA contracts.
Charlotte’s agreement is for a 35 MW installation, set to be built within the city. Bank of America agreed to a 25 MW project in the Piedmont region, and Duke University came to terms on a 101 MW deal from three solar facilities in the state.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.