The world has tremendous renewable energy resources, but often those resources are found far from population centers. For example, the best wind resources in the U.S. can be found in the panhandles of Texas and Oklahoma, as well as throughout the sparsely populated central Midwest. Likewise, many of the world’s best solar resources can be found in sparsely populated desert regions.
The U.S. National Renewable Energy Laboratory (NREL) has stated that large-scale deployment of renewable electricity generation will require additional transmission lines to relieve regional constraints.
In fact, there has been tremendous interest in linking up some of these rich renewable resources with population centers via transmission lines, but the costs are often prohibitive. These infrastructure projects are generally multibillion-dollar projects that must also win over approval from regulators and landowners.
Perhaps the most ambitious such project to date is the proposed Australia–ASEAN power line. This project would combine the world’s largest solar farm, the largest battery, and longest undersea electricity cable. Sun Cable, a Singapore-based company founded in 2018, is behind the proposed $16 billion project.
A 10-GW solar farm
The 10 -GW solar farm would cover 30,000 acres in Australia’s sunny Northern Territory. That is the equivalent of 9 million rooftop solar PV panels. The solar farm would be paired with a 30-GWh battery storage facility to enable round-the-clock dispatch of renewable power.
For perspective, the storage facility would be 155 times larger than Australia’s 193.5-MWh Hornsdale Power Reserve, currently the world’s largest operational lithium-ion battery. It would be 100 times larger than the world’s largest utility-scale battery, the 300-MWh sodium-sulfur battery at Japan’s Buzen Substation.
The high-voltage, direct current (HVDC) electric power cable will also be a major undertaking. The project currently envisions an 800 kilometer (km) overhead power line to transmit 3 GW to Darwin on the northern coast of Australia’s Northern Territory. From there, it would transfer to a 3,700-km 2.2-GW undersea power line to Singapore. Again, for perspective, this would be five times longer than the world’s longest undersea HVDC cable, the 720 km Norway-to-Britain North Sea Link that is scheduled to be online in 2021.
The project is scheduled to come online by the end of 2027. The project’s developers expect it to create up to 1,500 jobs during the construction phase, and up to 350 jobs during operations.
Challenges and costs
Given the interest in these types of projects, it is important to understand the challenges and ultimate cost of transporting renewable energy over long distances. The ability to do this economically has important ramifications from the Sahara Desert to the American Midwest to the Arctic.
To estimate the cost of the solar power produced by this system, we must make a few assumptions. The first is on the lifetime of the system. A general rule of thumb is that solar PV systems will last about 25 years. These systems can still produce power beyond that time frame, but significant degradation in the power output will occur by then.
Second, the amount of power produced over that time must be estimated. The capacity factor represents the percentage of energy generated over a period (normally a year) divided by the installed capacity. Because the sun’s output varies throughout the day and year – and according to location – the capacity factor for solar PV can vary from about 10% to 25%.
For example, if the 10 GW system could run at full output 24 hours a day, it could generate 24 x 365 x 10 = 87,600 GWh per year. Across Australia the average capacity factor for large-scale PV systems is estimated at 21%. Given the scale and location of the Sun Cable project, it’s not unreasonable to assume they could reach the upper range of 25% capacity factor.
In that case, over the lifetime of the system, it would produce 87,600 GWh * 25 years * 25% capacity factor = 547,500 GWh of power, or 547.5 terawatt hours (TWh).
There are also line losses to consider. Although direct current is a more efficient means of transmitting power over long distances than alternating current, some of the power transmitted is lost as heat. For DC, those line losses are dependent on the voltage of the line and the distance over which the power is transmitted. Most HVDC lines use voltages between 100 kilovolts (kV) and 800 kV. Given the power and distance traveled, the Australia-ASEAN Power Link will probably be on the upper end of that scale.
Siemens has stated that for 2.5 GW of power transmitted on 800 km of overhead line, the line loss at 800 kV HVDC is just 2.6%. Extrapolating that to the full length of the 4,500 km line would imply an overall power loss of 14.6%.
Thus, the overall delivered power could be estimated at 467.6 TWh. Then the simple levelized cost of the power produced from this project would be $16 billion divided by 467.6 TWh (which is equivalent to 467.6 billion kilowatt hours), or $0.034/kWh.
That is an attractive price, but it only provides a simple, low-end cost of the capital cost contribution to the project. This would need to be added to the ongoing maintenance costs – some of which could be significant if the undersea cable requires repairs – and financing costs. Available solar subsidies, which have also not been considered, could partially defray these costs.
***
Robert Rapier is a chemical engineer in the energy industry. Robert has 25 years of international engineering experience in the chemicals, oil and gas, and renewable energy industries, and holds several patents related to his work.
This article was originally published on The 4th Generation.
The views and opinions expressed in this article are the author’s own, and do not necessarily reflect those held by pv magazine.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
Malasia or Indonesia to Singapore transmission lines would have less line loss and be less costly and quicker to build.
Not all of the power will (or can) be delivered to Singapore on a 2.2GW HVDC line. Your assumed 25% utilization factor suggests an average rate of production of 2.5GW, the planned battery is large enough to deliver at that rate day and night, but it can’t absorb seasonal variation. So power sales will be higher in the southern Summer and lower in its winter. On a summer afternoon, there will be a lot more than 2.2GW of power to sell.
The effect of this is that much of the power will be sold into the Australian market and not all of the power will suffer the full transmission losses you estimate.
I wonder how big the power market is on Northern Australia. Not huge would be my guess. Australian grid operators may want to add some transmission capacity of their own. Even more than the generation, the storage could be a big help in maintaining grid reliability.
The world’s most ambitious renewable energy project to date is the proposed Australia–ASEAN Power Link. This project would combine the world’s largest solar farm, the largest battery, and longest undersea electricity cable. The 10 gigawatt (GW) solar farm would cover 30,000 acres in Australia’s sunny Northern Territory. That is about the equivalent of 9 million rooftop solar photovoltaic (PV) panels. The solar farm would be paired with a 30 gigawatt-hour (GWh) battery storage facility to enable round-the-clock dispatch of renewable power.