D. E. Shaw Renewable Investments (DESRI) has acquired First Solar’s 11 MW Rancho Seco Solar Project in Sacramento County, California, for an undisclosed amount.

Rancho Seco Solar is located on the site of the decommissioned Rancho Seco nuclear power plant, on 60 acres of property owned by the Sacramento Municipal Utility District (SMUD). SMUD holds a 20-year power purchase agreement for energy from the plant.

Equipped with First Solar’s thin-film modules mounted on single-axis tracking, Rancho Seco is expected to produce more than 23 gigawatt-hours of electricity annually.

Rancho Seco is set to provide energy for SMUD’s commercial SolarShares program. Through the program, the Golden 1 Center, currently under construction for the Sacramento Kings basketball team, will obtain approximately 85% of its power from Rancho Seco, making it one of the greenest sports arenas in the world, according to First Solar.

“We are pleased to buy another First Solar project and incorporate their leading edge equipment into our operating fleet,” said DESRI CEO Bryan Martin, adding that the company looked forward to partnering with First Solar on more opportunities in the future.

Earlier this year, a DESRI affiliate acquired from First Solar the 31 MW-AC Portal Ridge solar project, currently in construction in Lancaster, California.

Brian Kunz, First Solar’s vice president of project development, said the latest deal built on the company’s relationship with DESRI and added, “DESRI’s commitment to renewable solar energy represents a tremendous opportunity for a continued strategic partnership.”

DESRI’s portfolio of renewable energy projects currently includes 25 wind and solar projects that represent more than 1.2 GW of aggregate capacity.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Popular content

U.S. Congressmen introduce bill to block implementation of 45X tax credit
21 November 2024 Congressmen John Moolenaar and Jared Golden introduced a new bill that aims to halt advanced manufacturing tax credits.